Thoughtful Construction · Uppasite, Pont, Lanteglos-by-FoweyPrepared 21 October 2026 · figures from the project workbook

Uppasite build: cost and time to each milestone

—

Roofed shell

—
inc VAT · — after excavator sale
— of your working days · reached —

Wind and watertight

—
inc VAT · — after excavator sale
— of your working days · reached —

House complete

—
inc VAT · — after excavator sale
— of your working days · reached —

Everything, with the workshop

—
inc VAT · — after excavator sale
— of your working days

Money by phase: each bar is the running total

Inc VAT, with 16% for fixings, delivery and contingency. The darker part is what that phase adds; the pale part is everything before it. Hover for the phase on its own.

Programme: who is doing what, week by week

Working days on the placeholder start. Your tasks in colour; waiting on others in grey. Milestone lines mark the three stages above.

Cash: what must be spent, month by month

Running total needed, inc VAT, against the excavator money. The gap between the lines is what you borrow or add.

Running total neededFunds (excavator sale)

Day by day: what you'd be doing

Every task split into steps, one step a day, on the placeholder start. Grey items are other people's lead times running alongside. Weekends are left clear.

—

Budget by stage, ex VAT

Before on-costs. "Awaits engineer" is money whose size the structural engineer still sets; "allowance" is a guess with no quote behind it.

StageBudget (£)Awaits engineer (£)Allowance (£)Share

All figures are extracts from Uppasite-project.xlsx (the project workbook) as it stood when they were uploaded. Dates hang off the placeholder start of 2 November 2026 and assume one person working five days a week, one task at a time, with no holidays. No structural engineer has sized the structure yet.